3.5.1.6.2 Estimated Cost
The estimation result of project supervision cost is shown in the following table. Total
cost amounts to approximately JPY 630 million, among which detailed design and
procurement supervision comprises JPY 360 million and soft component JPY 270
million.
Table 3-42 Cost for project supervision
Item
Amount in JPY million
TOTAL (project supervision)
631
(1) Detailed design and Procurement supervision
381
(i) Remuneration (including indirect cost)
277
(ii) Direct cost
104
(2) Soft Component
250
(i) Remuneration (including indirect cost)
(ii) Direct cost
197
53
Source: Preparatory Survey Team
115