3.5.1.5 Cost for Usage charge of Container DC
3.5.1.5.1 Method for Cost Estimation
This is the expense for using the additional three racks in the container data center
for the Phase 2 development period for 20 months.
3.5.1.5.2 Estimated Costs
Total cost for container DC amounts to approximately JPY 0.02 billion.
Table 3-41 Cost for Container DC
Item
Calculation
TOTAL (procurement and construction)
(1)+(2)
19
(i)+(ii)+(iii)
19
(1) Purchase
Amount in JPY million
(i) Equipment
19
(ii) Installation
0
(iii) Procurement management
0
(2) Administrative expense
0
Source: Preparatory Survey Team
3.5.1.6 Cost for Project Supervision
3.5.1.6.1 Method for Cost Estimation
Project supervision cost includes two elements:
Detailed design and Procurement supervision
Soft component
Each of the elements consists of consultant remuneration and direct expenses.
The consultant remuneration is estimated for each consultant and task, which is
defined by the statement of work. The project direct expense is accumulated by item
of expenditures, travel, accommodations, and other expenses.
114