3.5.1.6.2 Estimated Cost The estimation result of project supervision cost is shown in the following table. Total cost amounts to approximately JPY 630 million, among which detailed design and procurement supervision comprises JPY 360 million and soft component JPY 270 million. Table 3-42 Cost for project supervision Item Amount in JPY million TOTAL (project supervision) 631 (1) Detailed design and Procurement supervision 381 (i) Remuneration (including indirect cost) 277 (ii) Direct cost 104 (2) Soft Component 250 (i) Remuneration (including indirect cost) (ii) Direct cost 197 53 Source: Preparatory Survey Team 115