3.5.1.5 Cost for Usage charge of Container DC 3.5.1.5.1 Method for Cost Estimation This is the expense for using the additional three racks in the container data center for the Phase 2 development period for 20 months. 3.5.1.5.2 Estimated Costs Total cost for container DC amounts to approximately JPY 0.02 billion. Table 3-41 Cost for Container DC Item Calculation TOTAL (procurement and construction) (1)+(2) 19 (i)+(ii)+(iii) 19 (1) Purchase Amount in JPY million (i) Equipment 19 (ii) Installation 0 (iii) Procurement management 0 (2) Administrative expense 0 Source: Preparatory Survey Team 3.5.1.6 Cost for Project Supervision 3.5.1.6.1 Method for Cost Estimation Project supervision cost includes two elements:  Detailed design and Procurement supervision  Soft component Each of the elements consists of consultant remuneration and direct expenses. The consultant remuneration is estimated for each consultant and task, which is defined by the statement of work. The project direct expense is accumulated by item of expenditures, travel, accommodations, and other expenses. 114

Select target paragraph3