• System security policy
• Cheque Truncation
• Disaster Recovery (Business Continuity Plan), etc.
2)
Advise to facility development of CBM-NET Phase 2
• Server room in Nay Pyi Taw for DR site
• New CBN-NET WAN for CBM-NET Phase 2
3)
Development of supporting system for CBM-NET Phase 2
• PSSD system
• Connecting with external systems
4)
Development of capacity of operation and maintenance of CBM-NET Phase
2
• In-house maintenance service
• Maintenance cost reduction measures
3.2.4.9 Implementation Schedule
The schedule for system development is assumed as shown in the figure below.
Starting from the completion of the consultant contract (expected in May 2018), CBM
will conclude a contract with application developers about two months later (Jul.
2018) and start development from the third month (Aug. 2018). On the other hand,
for infrastructure suppliers who will be selected by competitive bidding, it is
assumed that the selection of suppliers and the conclusion of contracts are completed
at the end of the third month, and infrastructure development will be started from
the fourth month (Sep. 2018). The development period of infrastructure is assumed
to be about ten months (Jun 2019), and after completion, the environment is released
to the application developers, and the application test is carried out. Application
development is assumed to be completed by the 19th month (Dec. 2019), the
environment will be open to CBM from the 20th month (Jan. 2020), and the
acceptance tests will be carried out. At the end of the 24th month (May 2020), the
first release is conducted, and the services with major functions are provided. The
additional functions and preparation of the STP with the FI of the second group are
conducted afterwards, and the second release will be conducted by the 30th month
(Nov. 2020), then it is assumed that the project is completed.
96