(C) System Test System tests will be carried under the CBM-NET Phase 2 application vendor's responsibility. The CBM-NET Phase 2 application vendor shall develop the test plan, conduct the system test, and report the test result to CBM according to the vendor's implementation and management methodology. The system test must be conducted in Myanmar using the new system environment. All functions shall be tested and non-function verification of system operation and performance shall be cleared by the CBM-NET Phase 2 application vendor. The infrastructure vendor will support the operation of the hardware and software. In this test, the following items must to be confirmed in addition to normal operation.  Switching to DR system  Processing using disaster recovery system after switching (D) Connection Test 1 Connection Test 1 is a test with group 1 FIs and will be carried out in parallel with the system test. In the connection test, the test performer confirms that the STP transaction is processed according to the specification in an environment where the CBS of each participating FI and CBM-NET are connected via GWs. This test is carried out under the responsibility of the CBM-NET Phase 2 application vendor with the participation of FIs. The CBM-NET Phase 2 application vendor will develop the test plan and lead this test. Processing in the CBS and GW of each participating FI must be confirmed under the responsibility of each participating FI before this test is started. In this test, the CBM-NET Phase 2 application vendor and each participating FI will 91

Select target paragraph3