Final Report
Chapter 9 Environmental and Social Considerations
The EIA report shall cover the following matters:
Brief introduction of the project implementing agency/developer and environmental and
social experts
Policies and legal/institutional framework
Explanation of the project and selection of alternatives
Explanation of the local environment
Impact and risk assessment and alleviating measures
Cumulative impact assessment
Environmental Management Plan (EMP)
Public consultation and disclosure
The EIA report shall be submitted to the Ministry of Environmental Conservation and
Forestry, which shall announce the availability of the EIA report on its website and invite
comments and recommendations on the EIA report from related agencies and society at large
so that the final decision regarding approval of the proposed report can be made on the basis
of such comments and recommendations. This decision-making process shall also be made
public.
Approval of the Project
The Ministry of Environmental Conservation and Forestry will issue an Environmental
Compliance Certificate (ECC) (valid for 2 years), and the Myanmar Investment Commission
(MIC) and other related agencies may not approve any project for which no ECC has been
issued.
The Ministry of Environmental Conservation and Forestry may require a review of the
Environmental Management Plan (EMP) in which case the project implementing agency
shall submit a revised EMP.
The project owner shall employ its contractors, subcontractors, officers, employees, agents,
representatives and consultants, and represent the project in the execution of the works for
the project for which the EMP has been approved, and shall take full legal and financial
responsibility for all detrimental impacts, actions and omissions occurring under the project.
The project owner shall carry out in their entirety the EMP, all project commitments and
requirements, and shall take responsibility for ensuring that all the contractors and
subcontractors for the project conform in full to all the applicable laws, the EMP, the project
contracts and requirements.
The project implementing agency/project owner shall be responsible for all the requirements
as provided in the Environmental Compliance Certificate, and in the applicable laws and
standards.
Monitoring
The project owner shall monitor the environmental impacts of the project in accordance with
the ECC, the EMP and applicable laws and standards during the period of implementation of
the project (before construction, during construction and operation, on abolition and
termination, and after termination), and shall submit the monitoring report in the form
9-8