Final Report
4)
Chapter 8 Project Implementation Plan
O&M System
O&M activities for the daily and the periodical is carried out by MPT staffs.
5)
Procedure of trouble reporting
MPT staffs generally cope with the troubles but for serious problems venders would support
to cope with. The group in charge will report to the superior according to the trouble happened.
The group in charge will handle any logic troubles but for the physical troubles of the
transmission line, LD or Auto Tel staffs would support to solve the problems.
6)
Training
More staffs in new technology field would be necessary for MPT to cope with the
introduction of new equipment with new technology, especially, Server/Core Router/Security
(Firewall) etc. Proper training, therefore, would be indispensable. Strengthening, in future,
supervising structure of network in Yangon, Nypyitaw and Mandalay, MPT shall increase his
staffs.
7)
Training Program
Long term program with consistent logic would be needed for new engineer’s training
program as described above in 6) and it would be necessary to have 3 to 6 months of training
periods or one year as the case. The request of training from IT Department in Yangon region is as
follows:
(i) Training Course
(a) Customer Handling Course
・Trouble Shooting
・Capacity Dimensioning & Expansion
(b) System Designing Course
・Security (Firewall etc.)
・IPv4 to IPv6
・Cloud
(ii) Staff for Training
IT dDepartment in Yangon region desires to make training for their staffs (incl. new) of each
section as requested in the table below which is proposed to high places as a staff training plan
8-17