Draft Final Report
Chapter 7 Outline of Scope of Works
Present monitoring systems are individually operated by each department, each vender and
each area. Proposed NOC system, however, would be difficult to cover to integrate and analyze all
information data which is generated from different monitor systems mentioned above. The scope of
facility to cover for the project, therefore, would be as follows,
The proposed NOC system shall cover to manage only for newly constructed network.
However, the system can be integrated in the particular case that the existing network applies
standard technology of SNMP (Simple Network Management Protocol) etc., and MPT would
supply the necessary information for integration. For the network not to being integrated, remote
monitoring would be available by separating the monitoring device in NOC, using the signal sent
through the monitoring network (DCN: Data Communication Network).
Main process necessary to offer those facilities is as follows,
Installation of servers and monitors
Setting and maintenance of monitoring network (An outline of the monitoring network is
shown in Figure 7.1-19.)
Monitoring control operated in the existing NMS shall be set up to be able to operate at
the servers and monitors which are installed in NOC.
Building up data base and data analysis system
Building up reporting system
NOC will be established in the new Hantharwaddy building in Yangon as a backup station for
improving reliability.
(4)
Equipment to be introduced
NOC will be constructed by the following three processes.
(a) Construction of main station (Naypyitaw, Dekkhina Exchange):
Main equipment (hardware): PC server, Network devices
Software: Platform, Database, Applications, Interface
Incidental facilities: Power supply system, Air conditioning system
Security: Physical, logical
(b) Establishment of backup station (Yangon, Hantharwaddy Station):
Main equipment (hardware): PC server, Network devices
Software: Platform, Database, Applications, Interface
Incidental facilities: Power supply system, Air conditioning system
Security: Physical, logical
(c) System integration
(5)
Main station: for backup station functional integration, testing
Main station: for backup station general coordination testing
Others