Final Report
Chapter 7 Outline of Scope of Works
Table 7.1-2 Naypyitaw Metro New Fiber Routes
No.
Routes
Distance
(km)
Ducts
(Note 1)
(mm× pipe)
Optical
Cables
Laying
Method
Spare Core in
existing cable
1 PMN - LW Ex:
17.0
24 Core
Aerial
0ew installation
2 LW - EL Ex;
25.0
24 Core
Aerial
New installation
3 TK - IGW
25.0
24 Core
Aerial
New installation
20.0
24 Core
Aerial
New installation
5 YZ - PL BTS
25.0
24 Core
Aerial
New installation
6 DKNTR - EL Ex;
35.0
24 Core
Aerial
New installation
7 ZYTR PSA - IGW
15
24 Core
Aerial
New installation
8 PBTR - TK Micro
40
24 Core
Aerial
New installation
4
ZYTR (Pyi San Aung
BTS) - YZ BTS
Sub Total 24 core
202.0
9 PMN - PL BTS
5.0
100φ×4
48 Core
U/G Laying
New installation
10 PMN -NPT Council
3.5
100φ×4
48 Core
U/G Laying
New installation
11 NPT Council - DKNTR
30.0
100φ×4
48 Core
U/G Laying
New installation
12 LW - DKNTR
10.0
100φ×4
48 Core
U/G Laying
New installation
13 DKNTR - BK RSU1
30.0
100φ×4
48 Core
U/G Laying
New installation
14 DKNTR - RSU13
30.0
100φ×4
48 Core
U/G Laying
New installation
15 RSU 3 - RSU 13
4.5
100φ×4
48 Core
U/G Laying
New installation
16 PMN - PBTR
20
100φ×4
48 Core
U/G Laying
New installation
17 PMN - TPK RSU 22
13
100φ×4
48 Core
U/G Laying
New installation
18 BK RSU1 - RSU 13
10
100φ×4
48 Core
U/G Laying
New installation
19 PBTR - ZYTR PSA
20
100φ×4
48 Core
U/G Laying
New installation
20 DKNTR - NPT S12
15.0
100φ×4
48 Core
U/G Laying
New installation
21 TPK RSU22 - NPT S12
10.0
100φ×4
48 Core
U/G Laying
New installation
22 PBTR - OTRTR
12.0
100φ×4
48 Core
U/G Laying
New installation
23 OTRTR - NPT S12
35
100φ×4
48 Core
U/G Laying
New installation
24 NPT S12 - RSU 3
10
100φ×4
48 Core
U/G Laying
New installation
Sub Total 48core
258.0
Summary
Fiber Optic 24core
202.0
Fiber Optic 48core
258.0
Cable duct 100φ×4
258.0
(Note 1): Unit for 100 is mm andφshows diameter.
7-13