Delays in Demolishing Unsafe Structures
On May 27, 2025, junta officials sealed Gattan Mosque in Sagaing after it was damaged in the
earthquake, amid a dispute with local police over ownership of the site. BHRN classified the mosque
as moderately damaged.49
In Bone Oh Village, Amarapura Township, a community representative said three of eight mosques
had completely collapsed or been reduced to the ground, while the remaining five had sustained major
damage requiring repair or reconstruction. Asked whether any had received demolition permission,
he replied, “Not a single one.” He said community representatives, local groups, and villagers had
repeatedly approached officials without obtaining permission. At one mosque, after the women's
section collapsed, the community demolished the men's section without permission. He said another
mosque was similarly demolished, creating complications for other mosque applications.50
The same representative said the Arabic Science School in Bone Oh had also collapsed. The
community applied for permission to remove the remaining walls and damaged structures. Officials
said permission would be issued within a few days, but by June 15, 2025, the community had still not
received it.51 He said most prayer facilities in the village remained temporary, with worshippers using
only two or three mosque buildings.52
Community representatives repeatedly sought permission through township, district, and regional
junta-controlled offices. A representative said a newspaper report after the earthquake stated that
affected religious buildings could be rebuilt according to their original designs, but the announcement
had not translated into permission locally. “That is the only announcement I have seen saying that
permission would be granted,” he told BHRN. “In practice, however, the announcement has not
reached us on the ground.”53
A Mandalay trustee told BHRN that junta officials initially issued demolition orders for 33 mosques
after the earthquake. When other mosques were submitted, officials did not issue demolition orders
and instead instructed applicants to obtain religious-land designation and apply for construction
permits. By September 13, 2026, the trustee said only about four to six of the original 33 cases had
made meaningful progress through the approval process.54
Another Mandalay trustee said more than 70 mosques across the city had submitted applications by
September 13, 2026. He said only four mosques had received repair permission, while Panthay
Mosque was the only mosque he identified as having received permission to rebuild from scratch.
“There are more than 70 mosques. Only four have received permission, so there are still many left,”
he told BHRN, referring to repair permissions.55
49 Myanmar Now, “Junta seals off earthquake-damaged mosque in Sagaing,” 30 May 2025.
50 BHRN Interview 12, Myanmar, 15 June 2025.
51 BHRN Interview 12, Myanmar, 15 June 2025.
52 BHRN Interview 12, Myanmar, 15 June 2025.
53 BHRN Interview 12, Myanmar, 15 June 2025.
54 BHRN Interview 15, Myanmar, 13 September 2026.
55 BHRN Interview 17, Myanmar, 13 September 2026.