3.5 Project Initial Cost Estimation
3.5.1 Initial Cost Estimation Breakdown
3.5.1.1 Policy for Cost Estimation
Cost estimations for goods and services to be procured under competitive tendering
procedure batch were based on the quotations obtained from multi-potential vendors
and suppliers. For goods and services planned to be procured under a single source
method, the survey team examined the elements of the elaborated cost breakdown
as provided by the single vendor and supplier.
3.5.1.2 Composition of the Project Cost
The project costs consist of the procurement cost and the project supervision cost.
The procurement cost includes the purchase cost and indirect cost. The project
supervision cost includes planning, procurement management, and soft components.
Equipment
Purchase
Procurement and
construction
Equipment
cost
Administrative
expense
Total cost
Maintenance
fee
Installation
Procurement
management
Detailed design
Design and
supervision
Design and
supervision of
equipment
Procurement
supervision
Soft component
Source: Preparatory Survey Team
Figure 3-39 Composition of project cost