On the other hand, the system infrastructure is procured by competitive tender bids.
This is because the equipment to be supplied from this batch is mostly composed of
off-the-shelf products. The equipment therefore may be procured from a number of
suppliers. It is for this reason that this batch is procured under the competitive
tendering procedure.
3.2.4.7 Operational Guidance Plan
3.2.4.7.1 Test and Transition Plan
Implementation of CBM-NET Phase 2 will conform to the following tests steps:
1.
Unit Test/Integration Test (integrated functional test)
2.
System Test
3.
Connection Test with FIs for STP
Connection tests will be held two times. Connection Test 1 (start from Oct. 2019)
is a connection test with group 1 FIs and Connection Test 2 (start from Jun.
2020) is with group 2 FIs.
The definition of each group is as follows;
Group 1: FIs that can prepare their STP environment (ready to connect)
prior to the Oct. 2019.
Group 2: FIs that can prepare their STP environment (ready to connect)
prior to the Jun. 2020.
4.
User Acceptance Test
5.
Running Test
Running tests will be held two times. Running Test 1 is for group 1 (will be golive from Mar. 2020) and Running Test 2 is for group 2 (will be go-live from Sep.
2020).
Unit test/integration test, system test, and connection test with FIs for STP will be
carried under the CBM-NET Phase 2 application vendor's responsibility.
Connection tests after Connection Test 2 and running tests after Running Test 2 (for
FIs that cannot prepare their STP environment until test/integration test, system
test, and connection test with beginning of the Connection Test 2) will not be included
89