(h) Any costs for the system after the go-live, such as changes in the
settings for enhancing the function of the system
3. Other
(a) All other obligations written in Annex 4 “Major undertakings to be
taken by the government of Myanmar”
(b) Collaboration on discussion and decision on system features
(c) Correspondence and communication with the users of FIs and CBM
(d) Issuance of new rules regarding to Phase 2 development functions
(e) Issuance of business continuity plan (BCP)
3.1.2 Project Timetable
The design and development phase (“System design finalization” and “Development
and tests” of below Figure) will commence from the 4th month after the signing of
G/A and will continue for 17 months. The system will be handed over to CBM by the
22nd month after the signing of G/A. System operation will commence with the first
go-live from the 25th month and then the second go-live will take after the first one
in the 31st month from the signing of G/A.
Source: Preparatory Survey Team
Figure 3-1 Overall timetable of the project
17