・ Business planning and application support D (Application D)
: Same as Application B
・ IT system infrastructure support A (Infra A)
: Lecturer in charge.
・ IT system infrastructure support B (Infra B)
: Same as Infra A. Q&A in the area of expertise.
14.4 Support for testing with FIs
Consultants support for CBM to do explanation to FIs, administrative arrangements and etc.
in the phase of connection test with FIs and running test.
Person month plan (unit: person months)
Operation
Support Leader
Application A
Application B
Application C
Application D
JPN
MMR
JPN
MMR
JPN
MMR
JPN
MMR
JPN
MMR
0
0.2
0
0
0
0.4
0
0.4
0
0.4
Application E
Application F
Infra A
Infra B
Infra C
Infra D
JPN
MMR
JPN
MMR
JPN
MMR
JPN
MMR
JPN
MMR
JPN
MMR
0
0
0
0
0
0.4
0
0.4
0
0
0
0
・ Operation Support Leader: Management of the work
・ Business planning and application support B (Application B)
: Explaining about the business and applications to FIs. also supporting administrative
arrangement.
・ Business planning and application support C (Application C)
: Same as Application B
・ Business planning and application support D (Application D)
: Same as Application B
・ IT system infrastructure support A (Infra A)
: Explaining about related infrastructure topics, also supporting administrative
arrangement.
・ IT system infrastructure support B (Infra B)
: Same as Infra A.
Task 15. Maintenance / operation support
15.1 Maintenance / operation plan
Consultants prepare the basic ideas of drawing up the plan for maintenance & operation after
the system launch in Japan, then instruct new creation or revising of materials for system
operations after discussion with AHRD members in Myanmar.
22