3.5.1.4 Cost for Infrastructure Development
3.5.1.4.1 Method for Cost Estimation
Infrastructure functions, which are mainly comprised of hardware equipment but
include software for infrastructure functions, are planned to be procured under
competitive tender procedures. Total costs for infrastructure function and relevant
equipment include the following elements:
Equipment
Maintenance fees for products (including expenses for three years after
handover)
Installation
Procurement management
Administrative expenses
3.5.1.4.2 Estimated Costs
Total costs for infrastructure functions amount to approximately JPY 2.07 billion.
One of the major costs is for HW and SW products, which are the equipment and
maintenance fees. Maintenance fee includes expense for three years after project
completion in addition to the development period (approximately 5 years in total).
Another major cost element is for installation. This includes not only the installation
of the system in the data center, but also installation of the network equipment in
the offices of CBM and FIs.
Table 3-40 Cost for infrastructure development
Item
Calculation
TOTAL (procurement and construction)
(1)+(2)
2,071
(i)+(ii)+(iii)
2,071
984
1087
0
0
(1) Purchase
(i) Equipment
(iii) Installation
(iv) Procurement management
(2) Administrative expense
Amount in JPY million
Source: Preparatory Survey Team
113